Formation of executive standard office facilities for a cutting edge technology client within an existing occupied premises.

The formation of a £1m executive Briefing Centre including reception, conferencing rooms, display area and associated breakout, toilet and kitchen facilities was undertaken as part of a two stage tender process required to meet exceptionally tight programme requirements, strict budgetary constraints whilst ensuring that quality would not be compromised.

Despite the works commencing on site three weeks later than originally anticipated, we worked closely with the client and their design team to facilitate a prompt and responsive flow of construction information. This in turn enabled the original programme completion date to be met and a “key critical” opening ceremony to be held and the facilities launched.

The effective management of this project directly resulted in a number of additional works within other areas of the complex. These ranged from multi-discipline projects through to specialist projects undertaken by our own internal divisions; manufacturing, building, M&E and decoration.

Client: Sun Micro Systems
Architect: BDG McColl
Value: £1m